Steel Taking Shape at the Los Angeles Convention Center
Structural steel is rising at the site of Los Angeles Convention Center’s Expansion and Modernization Project, and the numbers behind it reveal the story of a build of major proportions.
By the numbers
About 24,000 tons of primary structural steel — roughly 48 million pounds — will go into the build. For perspective, that's about half the steel used to build SoFi Stadium, according to ironworkers on the crew who also worked on that project.
The new Pico Hall will include 5,000 to 7,000 tons of earthquake-resistant bracing called Buckling-Restrained Braces.
The cranes
At the busiest point, four large cranes will be working on site simultaneously:
- One Manitowoc MLC650 — the heavyweight. One of only a handful of these cranes in North America, it can lift up to 716 tons.
- Two Liebherr LR 1300s — the workhorses. Each can lift about 330 tons and, in their tallest setup, can lift loads more than 550 feet into the air.
- One Liebherr LTR 1220 — the truss builder. It assembles the giant roof trusses on the ground before they're lifted into place.
The heaviest lift
Truss T210 weighs 250.9 tons — about 501,800 pounds. With its rigging attached, the full lift comes to 294.2 tons, or about 588,400 pounds.
This transfer truss spans an underground utility vault. Columns can't rest on top of the vault, so the truss has to carry the building's weight across it. The lift is too heavy for a single crane, so the MLC650 and an LR 1300 will lift it together in what crews call a "tandem pick" — a maneuver that takes precise coordination.
Steel erection will continue through the coming months as the expansion connects the South and West Exhibit Halls into one contiguous 750,000-square-foot space, keeping the project on track for completion in 2029.